Hydraulic engineering works to Sant'Elena Creek (P.782)

River defence and engineering works along the mouth of the Sant’Elena Creek, which runs alongside the Vado Ligure inland terminal area: restoration of the stretch of the river in question, with the expansion of the river run-off across drainage improvement works.

(Last refresh date 06.02.2023)

Project Code P.782
Project title Hydraulic engineering works to the Sant'Elena Creek in Vado Ligure
Project status
  
TTFS 
DD 
ED 
Start Works  
End Works 

 

Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design, activity completed  Activity completed activity in progress  Activity in progress  
Project value €4,500,000.00
Current activities Final Project Approval
Timeline Start Date: 1H 2023
Completion Date: 2H 2025