The new Mineral Oils berth (P.2933)

The project calls for the construction of the new Mineral Oils dock in the Port of Genoa across the reconfiguration of the quay to ensure safe vessel access (barges, bulk carriers up to LOA 130 m.

(Last refresh date 14.08.2024)

Project Code P.2933
Project title New mineral oils dock
Project status
  
TFFS 
DD 
ED 
Start Works 
End Works 
Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design, activity completed  Activity completed activity in progress  Activity in progress  
Project value €15,153,923.20
Current activities Works in progress
Timeline Start Date: May 2022
Completion Date: 2nd quarter 2024
Contractor Fincosit