News
30 January 2025
The Local Planning Board has given the go-ahead to the project plan variation submitted by the Port Authority for the construction of Genoa’s New Breakwater. The revised layout has been designed to ensure the...
30 January 2025
Refurbishment works are soon to be completed at Ponte Eritrea, the final phase of the extensive plan underway to upgrade and retrofit the quaywalls in Genoa’s Sampierdarena freight...
24 January 2025
The construction of the new 3-lane viaduct, connecting the Genova-Pra’ motorway exit directly to the container terminal facility, has been completed and is set to improve intermodal...
22 January 2025
The range of roadworks in progress across the Genoa-Sampierdarena port basin, to improve overall heavy goods vehicle accessibility to the terminal facilities, are near completion. The...
20 January 2025
The installation of the sixth caisson of Genoa’s new open-sea breakwater has been completed. A team of over 400 people are working on the project, including 150 offshore.