Thursday, 21 November 2024
EN
IT
News
Video
Infrastructure Works
Sustainability
Breakwater
Genoa's New Breakwater: works move ahead
01 July 2024
At a depth of 20 metres, the second caisson of the Port of Genoa's new breakwater has been successfully positioned. .........
New Breakwater: the first caisson successfully positioned
24 May 2024
Genoa, 24 May 2024 - The Port of Genoa's New Breakwater unfolds along the Sampierdarena basin, opposite the landmark 16th century Lighthouse. The first of the over 90 caissons, set to form part of the initial 4 km of the large-scale......
Genoa's New Breakwater's first floating caisson near completion
30 April 2024
The New Open-Sea Breakwater takes shape as the fast-paced construction of the caissons takes off, with the near-completion of the first of 100 caissons set to form the 6,200 metre port facility.
New Breakwater's first caisson under construction
03 April 2024
The construction of the first of 100 caissons, which will form Genoa’s New Open-Sea Breakwater, takes shape on board the “Dario” floating dock positioned in the Port of Vado Ligure. .....................
From the Breakwater to the Aquarium to protect the gorgonian coral
25 March 2024
As works for the construction of the Port of Genoa's New Breakwater proceed underwater, measures are taken to safeguard in full the marine ecosystem.
The New Breakwater unfolds along the seabed
06 February 2024
Genoa's New Breakwater begins to take shape in the open-sea, with 1 million tons of gravel deposited on the seabed. Construction works proceed on schedule. ............
New Genoa Breakwater, offshore construction works underway
01 December 2023
Work continues offshore on the New Genoa Breakwater, with the second block of columns under construction and 600,000 tons of gravel already deposited on the seabed.
New Breakwater: underwater construction of 850 giant columns
22 September 2023
The construction of the 850 columns is in its final stages, with a total of 370,000 tons of gravel laid on the seabed. Work on the second block of columns is now set to commence.
New Breakwater: underwater explosive hazards clearance goes ahead
01 August 2023
An underwater search for unexploded ordnances along the seabed, up to 50 metres in depth, has begun at Genoa's new open-sea breakwater site, in conjunction with a team of eight highly-experienced divers. ............
Laying of The First Stone for Genoa’s New Breakwater
04 May 2023
Western Ligurian Sea Port Authority and Per Genova Breakwater Consortium led by Webuild launch the project in the presence of Italian Infrastructure and Transport Minister Matteo Salvini. The Genoa’s New Breakwater is a national ......
Port of Genoa Breakwater: contract awarded to Webuild
12 October 2022
President Signorini: Construction works kick off in 2023. President Toti and Mayor Bucci: Momentous event set to revolutionise our port.
New Genoa Breakwater: two bids have been submitted
27 July 2022
As had already emerged from recent discussions, the two groups who had been invited by the Western Ligurian Sea Port Authority to tender for the elaboration of the detailed and executive design and the construction of the new Breakwater o......
New Genoa Breakwater: no bids submitted
01 July 2022
In view of the fact that no bids were submitted by the two groups pre-qualified to present an offer in the call for tender for the implementation of the detailed and executive design and construction of the new Breakwater of Genoa, the Po......
The tendering process for the construction of the New Breakwater kicks off
01 June 2022
On target, the Government Commissioner Paolo Emilio Signorini officially approved the technical and financial feasibility study for the project of Genoa's New Breakwater and today, 1st June 2022, the invitation letters to tender for......
ART visits the Ports of Genoa
31 May 2022
The President of the National Transport Regulation Authority, Nicola Zaccheo, flanked by the Board Directors Carla Roncallo and Francesco Parola and the Secretary General Guido Improta, met in Genoa with Western Ligurian Sea Port Authorit......
New Genoa Breakwater: Public Works Upper Council gives green light
31 May 2022
On 27 May the Select Committee of the Public Works Upper Council of the Ministry of Infrastructure and Sustainable Mobility gave the go-ahead to the Port of Genoa's key strategic project for the building of the New Breakwater. At this junc......
New Breakwater given official green light by EIA Ministerial Commission
12 April 2022
On 28 March the Technical Commission of the Italian Ministry of Ecological Transition issued the Environmental Impact Assessment final report, officially giving the go-ahead to the construction of the new breakwater in the Port of Genoa.
EIB funds Ports of Genoa development
10 December 2021
EIB promotes climate action by providing €300 million to finance Port of Genoa expansion This is the first EIB operation in Italy for a project co-financed by the government with resources from the Recovery and Resilience Facility Co.........
New Port of Genoa Breakwater: publication of call for expressions of interest
22 November 2021
The call for expressions of interest, to invite economic operators to apply to take part in the subsequent call for integrated tenders within the Project of the New Breakwater in the Port of Genoa, goes ahead. The integrated tender groups...
Port of Genoa Investment Programme forges ahead
24 August 2021
Project management of the new Breakwater has been contracted to RINA Consulting. Four tenders from the Investment Programme have been awarded in the last week, and an additional three are due to be announced shortly, for a total value of ......
Page 1 of 2
1
2
Next
News
Video
Infrastructure Works
Sustainability
News
Video
Infrastructure Works
Sustainability
Click to listen to the article