The project foresees the restructuring of the quaywalls and paving damaged by the seastorms in the Port of Savona, including the installation of new lighting systems.
(Last refresh date 24.01.2024)
The project foresees the restructuring of the quaywalls and paving damaged by the seastorms in the Port of Savona, including the installation of new lighting systems.
(Last refresh date 24.01.2024)
Project Code | P.773 |
---|---|
Project title | Restructuring of quaywalls in the Port of Savona |
Project status |
Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design, Activity completed Activity in progress
|
Project value | €550,000.00 |
Current activities | Material supply management for next phase of construction works. |
Timeline |
Start Date:
April 2022 Completion Date: 1Q 2024 |
Gallery |