Restructuring of westside Ponte Libia (P.3145)

Further to past structural damage, the project calls for the repaving of the westside quay line of Ponte Libia. Demolition work will be followed by the installation of an asphalt concrete surface.

(Last refresh date 05.05.2022)

Project Code P.3145
Project title Restructuring of westside Ponte Libia
Project status
  
TTFS 
DD 
ED 
Start Works 
End Works 

 

Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design, activity completed  Activity completed activity in progress  Activity in progress  
Project value € 155.000,00
Current activities Awarding procedures underway
Contractor Impresa Rebecchi Matteo