Rail link upgrade from Bettolo Terminal and PSA SECH Terminal to Campasso Rail Yard (Molo Nuovo Tunnel) (P.2930)

Upgrade of the direct on-terminal rail links from Bettolo and PSA SECH, with the construction of a double-track line between San Benigno/Bettolo and S. Limbania across the Molo Nuovo Tunnel. Works include the installation of a new signalling system, in compliance with the Rail Safety National Agency standards, and a new electric rail traction system.

(Last refresh date 14.08.2024)

Project Code P.2930
Project title Upgrade of the Campasso rail yard infrasctucture (Molo Nuovo Tunnel)
Project status
  
TFFS 
DD 
ED
 
Start Works 
End Works 
Project status key TFFS = Technical and Financial Feasibility Study, DD = Detailed Design, ED = Executive Design, activity completed  Activity completed activity in progress  Activity in progress  
Project value €17,800,000.00
Current activities Construction works in progress
Timeline Start Date Preparatory Works: July 2021 (track demolition)
Start Date: February 2023
Completion Date: April 2025
Contractor RTI Micos